I-35 Bridge Rehab Projects

The Missouri Department of Transportation announced a series of bridge rehabilitation projects along the Interstate 35 corridor.  The work is scheduled for five bridges in Clinton and Daviess counties. Capital Paving and Construction, working with MoDOT, plan to begin construction on the Daviess County Route KK bridge on Monday, May 20. The bridge will remain closed through early July.

Rehabilitation Schedule:

Clinton County

US 69 bridge south of Cameron – NOW thru early June

Daviess County

Route KK bridge – May 20 thru mid-July

Route DD bridge – Late June thru early Sept.

Route B/N bridge – Mid-Aug. thru late Oct.

Route C bridge – Late Aug. thru early Nov.

During the bridge projects, the bridges will be closed. Motorists should follow signed detour routes.

Interstate traffic will also be affected. For safety reasons, no traffic will be permitted under the bridges during demolition.  The traffic on the freeway will be routed up and over the on and off ramps at the exit. The demolition work is scheduled to occur during nighttime hours, between 9:00 pm and 6:00 am.