The resurfacing on Route 6 from US 69 to the Muddy Creek Bridge just east of US 65 in Trenton was delayed but will move into the City of Trenton beginning next week. Â Emery Sapp & Sons, Inc. is working to complete the multi-stage project to resurface and improve shoulders throughout the project limits and to rehabilitate sidewalks within the city of Trenton. Â Sidewalk rehabilitation within Trenton has been ongoing since the beginning of May and will continue through August.
The portion of the resurfacing project in Trenton on Route 6 from the railroad bridge to the Muddy Creek Bridge is expected to begin Monday. Â Â The portion of the road from Route V to Trenton will receive a different surface treatment under a separate contract. The schedule for that portion of the project has not yet been determined.
In Trenton, where the roadway is four-lanes wide, one lane each direction may be closed. A 12-foot width restriction throughout the project will be in place until all work is complete. Motorists will encounter delays and may wish to seek an alternate route.