The Chillicothe Board of Public Works approved two bids as part of its meeting Tuesday.
For the Electric Department, General Manager Matt Hopper says a bid was accepted for a Motor Control Center.
One bid from SMC for $61,025.
In the Waste Water Department, there was also one bid accepted.
For sandblasting and recoating of the ditch for $336,000
Work is expected to begin in October and should be completed in February.
Hopper says the annual audit report was presented, and there were no concerns.