Resurfacing Work On US 36 in Livingston County Postponed

Resurfacing work on US 36 in Livingston County has been postponed.  The work that had been expected to begin today (Monday) has been postponed a couple days, and should begin Wednesday.  The resurfacing project includes eastbound from Route C to Parson’s Creek, just over the Linn County line, and westbound from Parson’s Creek to Coon Creek.

The current schedule includes:

June 8 – 17: Concrete pavement repairs, both directions

June 20 – 30: Roadside work, westbound only, at the Leeper Creek Bridge, just east of Chillicothe

July 5 – Aug. 18: Guardrail work, both directions

Aug. 24 – Sept. 12: Pavement repairs, both directions

Sept. 6 – Oct. 27: Resurfacing, shoulder work, and striping, both directions

The roadway will remain open, but traffic may be reduced to a single lane in either direction.

All work is expected to be complete by the end of October.  A 16-foot width restriction will be in place for the duration of the project.