Contractors and the Missouri Department of Transportation plan to close three ramps on US 36 at US 65 on Sunday. The closures are part of a resurfacing project on US 36 led by Herzog Contracting Corp.
The ramps will not be closed simultaneously. These short-duration closures are planned for Sunday, when the number of vehicles using the ramps is lower, and to take advantage of favorable weather conditions.
The planned schedule includes:
Sunday:
- 7 – 11 a.m.: Westbound on-ramps
- 11 a.m. – 2:30 p.m.: Eastbound off-ramp
- 2:30 – 5:30 p.m.: Eastbound on-ramp
The westbound off-ramp was completed earlier this month.
All work is weather permitting,