Search

Stream KCHI Live 24/7!

Circle Drive, CES Sidewalks And Access Road

Completing the roads and sidewalks for the elementary school expansion and at the high school are taking place.   Superintendent Dr Dan Wiebers says at the high school the circle drive is closed.

Demo of the CHS circle drive is taking place with concrete to be poured next week.

Wiebers explains the concrete work to be done at CES as early as today.

Sidewalks at CES this week and the access road next week.

The concrete for the roadways will need about a week of curing before they will be available for traffic.