Resurfacing Scheduled In Four Counties

Several routes in Carroll, Linn, Livingston, and Sullivan counties will be resurfaced beginning next week. Emery Sapp & Sons, Inc., working with the Missouri Department of Transportation, plan to resurface the routes according to the schedule listed below:

  • Linn County Route 139 from the Parsons Creek to US 36: Aug. 29 – Sept. 6
  • Livingston/Linn County Route BB from Route KK to Route B: Sept. 2 – 7
  • Livingston County Route KK from Route BB to the end of state maintenance: Sept. 6 – 9
  • Livingston County Route JJ from US 65 to Route H: Sept. 12 – 19
  • Carroll County Route YY from Route J to Route M: Oct. 10 – 19
  • Carroll County Route C from Route D to Route Z: Oct. 17 – 27
  • Livingston/Carroll County Route Z from US 65 in Livingston County to US 65 in Carroll County: Oct. 21 – Nov. 7

During construction, motorists will be directed through the one-lane work zone by flaggers. A 10-foot width restriction will be in place while work zones are active. Crews will be present during daylight hours, Monday through Saturday. All work is weather permitting, and schedules are subject to change.

 

Three additional routes are also included in this bundle but will not be completed until 2023. Those routes are:

  • Grundy/Linn County Route 139 from Grundy County Route 6 to Parsons Creek, north of Linn County Route B
  • Grundy/Livingston Route K from Route E to US 65
  • Grundy/Livingston County Route U from Route F to Route 190
  • Livingston Route Y from Route W to Route 190