Today's News... Yesterday's Music

Today's News... Yesterday's Music

Construction Progress On New Police Facility

Construction of the new Chillicothe Police Facility progresses.  The contractor, Crossland Construction, says that in the month of June, they completed the iron work and placed the roof trusses, concrete walls and sally port have been constructed, and they are working on the studwork for interior walls and structural areas.

City Administrator Roze Frampton says they are happy with the progress.

Good both with construction and finances.

Frampton says the construction completion does not mean the move-in date.

Looking at an April move-in date.

The project has not been adversely affected by tariff-related supply issues.  Frampton says the contractor did have to resource one item.

News

April 17, 2026

Wastewater Smoke Testing Scheduled For Monday

News

April 17, 2026

6th Congressional District Candidate – Nathan Willette

News

April 17, 2026

Chillicothe FFA At State

News

April 17, 2026

CHS Art Contest Winners

News

April 17, 2026

Personnel Matters Handled In Chillicothe City Council Executive Session