MoDOT ADA Projects In Hamilton And Gallatin

Americans with Disabilities Act improvements and resurfacing of a portion of Missouri Route 13 between Gallatin and Hamilton was awarded to Herzog Contracting Corp. The work is expected to begin March 16th in Hamilton, with ADA Improvements that include curb ramps, sidewalk transitions, crosswalks and striped parking.  The ADA work will take place in Hamilton along Route 13 between Samuel Street and School Street, and in Gallatin on Route 13 between Berry Street and Van Buren Street.

The ADA improvements are scheduled to be completed by mid-April.  Once the ADA work is completed, crews will resurface Route 13 between Gallatin and Hamilton.

All work is anticipated to be completed by June 2026.

MoDOT says that as a part of this project, crews will also be resurfacing Route 69 in Clinton County. Scheduling details will be shared after the completion of work on Route 13.

News

November 23, 2026

80th Annual Chillicothe Holiday Parade Winners

News

November 23, 2026

Thanksgiving Holiday Travel

News

November 23, 2026

Jail Bookings For Livingston County

Funeral Announcements, News

November 23, 2026

Tony Neil Trammell

News

November 23, 2026

Two Injured In Two Crashed In The area Counties