Phase III Chillicothe Street Projects Awarded

The major street projects for the City of Chillicothe, known as Phase III, will cost nearly $1.8 million.  City Administrator says two streets are included.

  • Second Street from Washington to Ryan Street
  • Maple Street from 11th to Central

Both projects include concrete streets, curb and gutter, and sidewalks.

The contractor, M&M Utilities was awarded the contract that came in under the engineer’s estimate.

Work can begin when the utility relocation is completed.  CMU has already finished its portion.