Sullivan County BUILD Project Delayed

MoDOT Roadwork Scheduled in the Area

An intersection improvement project on Sullivan County Route 5 has been delayed for another week. The Missouri Department of Transportation (MoDOT) is administering a US D O T Better Utilizing Investments to Leverage Development (BUILD) grant for the construction of transportation improvements around the Roy Blunt Reservoir project. Contractors planned to begin the multi-stage project Monday, but are now planning to begin construction on August 14th.

The tentative schedule of work for the BUILD grant intersection improvements includes:

Aug. 14 – early November: Intersection improvements at Route 5 and Mid-Lake Road.  

Aug. 28 – late October: Intersection improvements on Route 5 at the intersections of Route N and Mayapple Road.  

As part of the BUILD grant, additional work is planned in the next two years in Sullivan County.

News

August 4, 2026

Federal Disaster Assistance For 34 Missouri Counties

News

August 4, 2026

Chillicothe Police Report For Monday

News

August 4, 2026

Carrollton Police Department To Be Abolished

News

August 4, 2026

Serious Injury Crash Near Jamesport

News

August 4, 2026

Missouri Primary Election Today