Contractors continue to make visible progress on the new Chillicothe Police Department building. The project manager reports that in October:
- Successful installation of ceiling grid throughout the building.
- Substantial progress on the installation of all window and door systems.
- The electrical team continues to make steady progress throughout the building, including light fixtures in the ceiling grid.
- The exterior insulation and finishing systems completed.
- HVAC contractors are on schedule to begin installation of the rooftop units (RTUs) by the end of the month.
- The flooring contractor has commenced tile installation within the restroom areas. The tile/flooring work will continue throughout the month of November.
Work planned in November includes:
- Installation of ceiling grid tile, ACM panels on the exterior, bathroom accessories and fixtures, and casework into early November.
- Finish up tile work, start on epoxy and carpet tile.
- Complete windows and doors, and install bulletproof glass.
The timeline shows completion is expected near the end of March.