Chillicothe Police Facility Construction Progress

Contractors continue to make visible progress on the new Chillicothe Police Department building.  The project manager reports that in October:

  • Successful installation of ceiling grid throughout the building.
  • Substantial progress on the installation of all window and door systems.
  • The electrical team continues to make steady progress throughout the building, including light fixtures in the ceiling grid.
  • The exterior insulation and finishing systems completed.
  • HVAC contractors are on schedule to begin installation of the rooftop units (RTUs) by the end of the month.
  • The flooring contractor has commenced tile installation within the restroom areas. The tile/flooring work will continue throughout the month of November.

Work planned in November includes:

  • Installation of ceiling grid tile, ACM panels on the exterior, bathroom accessories and fixtures, and casework into early November.
  • Finish up tile work, start on epoxy and carpet tile.
  • Complete windows and doors, and install bulletproof glass.

The timeline shows completion is expected near the end of March.

News

March 25, 2026

FAFSA Deadline For Access Missouri Grant

News

March 25, 2026

Booked On Probation Violation Warrant

News

March 25, 2026

Sullivan County Bridge Replacement

News

March 25, 2026

MoDOT Sidewalk Projects

News

March 24, 2026

Choir And Band Members Headed To MSHSAA State Music Contest