Sullivan County BUILD Project Delayed

MoDOT Roadwork Scheduled in the Area

An intersection improvement project on Sullivan County Route 5 has been delayed for another week. The Missouri Department of Transportation (MoDOT) is administering a US D O T Better Utilizing Investments to Leverage Development (BUILD) grant for the construction of transportation improvements around the Roy Blunt Reservoir project. Contractors planned to begin the multi-stage project Monday, but are now planning to begin construction on August 14th.

The tentative schedule of work for the BUILD grant intersection improvements includes:

Aug. 14 – early November: Intersection improvements at Route 5 and Mid-Lake Road.  

Aug. 28 – late October: Intersection improvements on Route 5 at the intersections of Route N and Mayapple Road.  

As part of the BUILD grant, additional work is planned in the next two years in Sullivan County.

Sports

July 11, 2026

Mudcats Walk-Off First Place Clarinda A’s on Saturday Evening

News

July 11, 2026

Sheriff’s Arrest Report

News

July 11, 2026

Trenton City Council Looks at Special Counsel

News

July 11, 2026

Good Weather for MoDOT Roadwork

News

July 11, 2026

Airport on City Council Agenda