Today's News... Yesterday's Music

Today's News... Yesterday's Music

US 36 Repaving Phase II Begins Tuesday

Phase one of the US 36 resurfacing project in Livingston County is complete.  Phase two begins Tuesday.  The Missouri Department of Transportation and the contractor are currently working on two concrete pavement replacements on US 36 under the US 65 bridge and the Canadian Pacific Railroad bridge.

Phase One is completed and the roadway is fully open for the Memorial Day holiday weekend.

Phase Two (May 28-June 14): Traffic will be restricted to one lane in the driving lane, both directions, for passing lane reconstruction.

Phase Three (June 15-July 12): Traffic will be restricted to one lane in the passing lane, both directions, for driving lane reconstruction.

Workers will be present during daylight hours, Monday through Friday, Saturdays as needed, weather permitting. A 17-foot width restriction will be in place. All work is expected to be complete by the end of July.

Sports

May 19, 2026

Hornets Track & Field Sending Several Athletes to State

News

May 19, 2026

Caldwell County Jail Booking

News

May 19, 2026

Water Main Repairs For 145 Customers

News

May 19, 2026

Flood Warning Updates

News

May 19, 2026

Chillicothe Police Report For Monday