Today's News... Yesterday's Music

Today's News... Yesterday's Music

MoDOT Low Volume Route Resurfacing

The Missouri Department of Transportation has scheduled resurfacing of low-volume rural routes in Linn and Sullivan counties. The project is scheduled to begin on Monday, with Route Y in Sullivan County.  Work will continue through mid-May on several roads.

During construction, roadways will be closed in sections up to 2-mile long. Motorists will need to seek an alternate route.

The contractor’s tentative schedule is as follows:

  • March 16-20: Sullivan County Route Y
  • March 23-April 3: Sullivan County Route OO
  • April 6-13: Sullivan County Route FF
  • April 13-17: Sullivan County Route H
  • April 20-27: Sullivan County Route Z
  • April 28-May 6: Sullivan/Linn County Route MM
  • May 7-16: Sullivan County Route DD

All work is weather-permitting, and schedules are subject to change.

Funeral Announcements

March 30, 2026

Dorothy L. Lindley

News

March 30, 2026

911 Services Director Selected For Livingston County

News

March 30, 2026

Lambert Appointed To State Soil And Water Districts Commission

News

March 30, 2026

Additional Election Filings In Livingston County

News

March 30, 2026

Charges Filed In Livingston County Court