New Chillicothe Police Facility Construction Progress Report

Progress on the new Chillicothe Police facility continues and construction appears to be on schedule.

The report from the contractor shows work is taking place both inside and outside.  They have completed drywall work and continue to prepare surfaces for finishing.

On the exterior, rock and brick work continue and they are also working on exterior fixtures, including electrical cabinets and the transformer pad.

During October, the contractor says projects include:

  • Concrete: Prep and pour curb/paving
  • Install windows and storefront systems
  • Install ceiling grid
  • Installation of ACM panels on the exterior of the building
  • Installation casework near the end of October

The timeline continues to show that various work will be completed late in the year, with the start of the punch list in February and expected completion at the end of March.

News

May 6, 2026

Livingston County Taking Steps Towards Requirements For Data Centers And Battery Storage

Sports

May 6, 2026

Hansen Provides Pivotal Victory

Sports

May 5, 2026

Hornets Golf Team Places 3rd in Conference Match

News

May 5, 2026

Variance Denial May End Up In Court

News

May 5, 2026

Bids Accepted In Two Water And Sewer Projects